Levee Lumber
Work done on 1004 Central:
Lumber supplier
Levee Lumber
Work done on 1004 Central:
Lumber supplier
Work done on 1004 Central:
Foundation coating and membrane.
Work done on 1004 Central:
Utilities (water, sewer lines) and some drainage pipe installation.
Work done on 1004 Central:
Plumbing
Work done on 1004 Central:
Installation of radiant tubing for heating system.
Work done on 1004 Central:
Windows & Doors (Marvin Integrity – fiberglass with wood interiors)
Work done on 1004 Central:
Flatwork for basement and garage slabs. Flatwork and polishing for main floor slab.
Work done on 1004 Central:
Gravel for underneath basement and garage slabs.
We met today with a green building consultant, Elly at O’Brien & Company in Seattle. O’Brien & Company offers a multitude of services related to sustainability and green building. They are also the LEED for Homes provider in Washington State.
The stormwater management plan for 1004 Central, both during construction and long-term, relies on low impact development techniques. The goals for stormwater management during and post-construction are different.